Quantitative Reasoning Time And Work MCQS Test Online Mock Quiz
Home / Tests / Quantitative Reasoning Time and Work MCQS Test Online

Quantitative Reasoning Time and Work MCQS Test Online

Test Name Quantitative Reasoning Test
Subject Aptitude
Test Type MCQS
Total Question 30
Total Marks 60
Total Time 30
Test Help For
  • GMAT
  • Bank Exam
  • All Jobs Test
  • All Entrance Exams
  • All Forces Quiz
  • CAT
  • GATE
  • GRE

Quantitative Reasoning Time and Work MCQS Test Online

Aptitude

1. mark reviewMr. Ram is on tour and he has ζ 360 for his expenses. If he exceeds his tour by 4 days he must cut down daily expenses by ζ 3. The number of days of Mr. Ram's tour programme is?

Question 1 of 15

2. mark reviewIf 5 men take an hour to dig a ditch, them how long should 12 men take to dig a ditch of the same type?

Question 2 of 15

3. mark reviewA and B weave a carpet in 10 days and 15 days respectively. They begin to work together but B leaves after 2 days. In what time will A complete the remaining work?

Question 3 of 15

4. mark reviewA contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. Then how many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Question 4 of 15

5. mark reviewA woman works continuously for 7 days in the kitchen and refuses to work on the 8th day when her husband takes over. If she starts her work on a sunday, the 10th time she rests will be on which day of the week?

Question 5 of 15

6. mark reviewA contractor undertakes to build a wall in 50 days. He employs 50 people for the same. However, after 25 days finds that the work is only 40% complete. How many more men need to be employed to complete the work in time?

Question 6 of 15

7. mark reviewA can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work?

Question 7 of 15

8. mark reviewA can do a work in 9 days. If B is 50% more efficient to A, then in how many days can B do the same work?

Question 8 of 15

9. mark reviewTwo men undertake to do a piece of work for ζ 600.One alone could do it in 6 days and the other in 8 days. With the assistance off a boy they finish it in 3 days. The boy's share should be?

Question 9 of 15

10. mark review1/3rd of the contents of a container evaporated on the 1st day.3/4th of the remaining evaporated on the second day. What part of the contents of the container is left at the end of the second day?

Question 10 of 15

11. mark reviewA contractor undertook to do a piece of work in 9 days. He employed certain number of laborers, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. Find the number of men originally employed?

Question 11 of 15

12. mark reviewA team of workers was employed by a  contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job?

Question 12 of 15

13. mark reviewTwo spinning machines A and B can together produce 3,00,000 meters of cloth in 10 hours. If machine B alone can produce the same amount of cloth in 15 hours, then how much cloth can machine A alone produce in 10 hours?

Question 13 of 15

14. mark reviewThe work done by a woman in 8 hours is equal to the work done by a man in 6 hours and by a boy in 12 hours. If working 6 hours per day 9 men can complete a work in 6 days, then in how many days can 12 men, 12 women and 12 boys together finish the same work, working 8 hours per day?

Question 14 of 15

15. mark reviewA can do 50% more work as B can do in the same time. B alone do a piece of work in 20 hours.A, with the help of B, can finish the same work in how many hours?

Question 15 of 15


 

Test By Subject
Test By Topics
Have any Problem or Error please mention in below comments section.

Leave a Reply

Your email address will not be published. Required fields are marked *