Home / Tests / Quantitative Reasoning Time and Work MCQS Test Online

Quantitative Reasoning Time and Work MCQS Test Online

Test Name Quantitative Reasoning Test
Subject Aptitude
Test Type MCQS
Total Question 30
Total Marks 60
Total Time 30
Test Help For
  • GMAT
  • Bank Exam
  • All Jobs Test
  • All Entrance Exams
  • All Forces Quiz
  • CAT
  • GATE
  • GRE

Quantitative Reasoning Time and Work MCQS Test Online

Aptitude

1. A contractor undertook to do a piece of work in 9 days. He employed certain number of laborers, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. Find the number of men originally employed?

Question 1 of 15

2. A and B can finish a job in 10 days while B and C can do it in 18 days. A started the job, worked for 5 days, then B worked for 10 days and the remaining job was finished by C in 15 days.In how many days could C alone have finished the whole job?

Question 2 of 15

3. A can do a work in 9 days. If B is 50% more efficient to A, then in how many days can B do the same work?

Question 3 of 15

4. Two men undertake to do a piece of work for ζ 600.One alone could do it in 6 days and the other in 8 days. With the assistance off a boy they finish it in 3 days. The boy's share should be?

Question 4 of 15

5. Two men undertake to do a piece of work for ζ 1,400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of boy, how should the money be divided?

Question 5 of 15

6. Two men and 7 children complete a certain piece of work in 4 days while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is ?

Question 6 of 15

7. A woman works continuously for 7 days in the kitchen and refuses to work on the 8th day when her husband takes over. If she starts her work on a sunday, the 10th time she rests will be on which day of the week?

Question 7 of 15

8. A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. Then how many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Question 8 of 15

9. Mr. Ram is on tour and he has ζ 360 for his expenses. If he exceeds his tour by 4 days he must cut down daily expenses by ζ 3. The number of days of Mr. Ram's tour programme is?

Question 9 of 15

10. A and B weave a carpet in 10 days and 15 days respectively. They begin to work together but B leaves after 2 days. In what time will A complete the remaining work?

Question 10 of 15

11. 1/3rd of the contents of a container evaporated on the 1st day.3/4th of the remaining evaporated on the second day. What part of the contents of the container is left at the end of the second day?

Question 11 of 15

12. A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work?

Question 12 of 15

13. If 600 men dig a 5.5 m wide, 4 m deep and 405 m long canal in half an hour, then how long a canal will 2500 men, working for 6 hrs, dig if it is 10 m wide and 8 m deep?

Question 13 of 15

14. 15 men can complete a work in 210 days. They started the work but at the end of 10 days 15 additional men, with double efficiency, were inducted. How many days in all did they take to finish the work?

Question 14 of 15

15. A team of workers was employed by a  contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job?

Question 15 of 15


 

Test By Subject
Test By Topics
Have any Problem or Error please mention in below comments section.

Leave a Reply

Your email address will not be published. Required fields are marked *