Home / Tests / Quantitative Reasoning Time and Work MCQS Test Online

Quantitative Reasoning Time and Work MCQS Test Online

Test Name Quantitative Reasoning Test
Subject Aptitude
Test Type MCQS
Total Question 30
Total Marks 60
Total Time 30
Test Help For
  • GMAT
  • Bank Exam
  • All Jobs Test
  • All Entrance Exams
  • All Forces Quiz
  • CAT
  • GATE
  • GRE

Quantitative Reasoning Time and Work MCQS Test Online

Aptitude

1. If 600 men dig a 5.5 m wide, 4 m deep and 405 m long canal in half an hour, then how long a canal will 2500 men, working for 6 hrs, dig if it is 10 m wide and 8 m deep?

Question 1 of 15

2. If 5 men take an hour to dig a ditch, them how long should 12 men take to dig a ditch of the same type?

Question 2 of 15

3. A certain number of people were supposed to complete a work in 24 days. The work however, took 32 days, since 9 people were absent throughout. How many people were supposed to be working originally?

Question 3 of 15

4. A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. Then how many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Question 4 of 15

5. A and B can finish a job in 10 days while B and C can do it in 18 days. A started the job, worked for 5 days, then B worked for 10 days and the remaining job was finished by C in 15 days.In how many days could C alone have finished the whole job?

Question 5 of 15

6. A and B together can do a piece of work in 6 days. A alone can do it in 10 days. What time will B require to do it alone?

Question 6 of 15

7. Large,medium and small ships are used to bring water. 4 large ships carry as much water as 7 small ships. 3 medium ships carry the same amount of water as 2 large ships and 1 small ship. 15 large,7 medium and 14 small ships, each made 36 journeys and brought a certain quantity of water. In how many journeys would 12 large, 14 medium and 21 small ships bring the same quantity?

Question 7 of 15

8. 1/3rd of the contents of a container evaporated on the 1st day.3/4th of the remaining evaporated on the second day. What part of the contents of the container is left at the end of the second day?

Question 8 of 15

9. A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work?

Question 9 of 15

10. A team of workers was employed by a  contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job?

Question 10 of 15

11. A contractor undertook to do a piece of work in 9 days. He employed certain number of laborers, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. Find the number of men originally employed?

Question 11 of 15

12. A child can do a piece of work 15 hours slower than a woman. The child works for 18 hours on the job and then the woman takes charge for 6 hours. In this manner, 3/5 of the work can be completed. To complete the hob now, how much time will the woman take?

Question 12 of 15

13. A can do a work in 9 days. If B is 50% more efficient to A, then in how many days can B do the same work?

Question 13 of 15

14. A woman works continuously for 7 days in the kitchen and refuses to work on the 8th day when her husband takes over. If she starts her work on a sunday, the 10th time she rests will be on which day of the week?

Question 14 of 15

15. 15 men can complete a work in 210 days. They started the work but at the end of 10 days 15 additional men, with double efficiency, were inducted. How many days in all did they take to finish the work?

Question 15 of 15


 

Test By Subject
Test By Topics
Have any Problem or Error please mention in below comments section.

Leave a Reply

Your email address will not be published. Required fields are marked *